Park Avenue Utility and Road Reconstruction – Village of Germantown
(Freistadt Rd. to Main St.)

This website will provide you with relevant information concerning the construction activities on the Park Avenue reconstruction project in the village of Germantown. The information provided on this website has been supplied to the Village by the project contractors and may change from what is listed, depending on weather conditions or varying job site conditions. If you require specific time-related information, please contact Mr. Mike Mentzel. He will be running the project for the Village of Germantown and can be reached at 262-317-3338 or by email at mike.mentzel@rasmith.com.

Please note that this website will not be updated on a daily basis, but rather as project conditions change. If you have time-specific questions, please contact Mr. Mike Mentzel who will be representing the Village of Germantown on the project.

 

Update: July 8, 2019

 

Tuesday, July 9 – Work on the project is scheduled to start with the closure of Park Avenue. All residents of Park Avenue will be allowed to access your properties for the majority of the project; however, traffic will not be allowed to use Park Avenue to go from Fond du Lac Avenue to Main Street.

Wednesday, July 10 – The existing asphalt pavement on Park Avenue will be removed. There is an existing layer of concrete pavement that will be left in place for residents to travel on.

Thursday, July 11 – The contractor intends to be on site to remove the trees on the west side of Park Avenue to allow for the reconfiguration of the roadway.

Monday, July 15 – The contractor intends to start work on the reconstruction of the sanitary sewer starting near the intersection of Park and Main Street and proceeding to Fond du Lac Avenue. Please note that you will have continuous sanitary sewer service during this work and that as a part of the project your existing sanitary sewer lateral will be reconnected to the new sanitary sewer main.  The contractor is anticipating that this work should take approximately 10 working days to complete.