Construction Limits:
C.T.H. "Q"; County Line Road from Colgate Road to C.T.H. "Y" (Lannon Road)
2007 Construction Information
Construction is scheduled to begin on C.T.H. "Q" on Monday, April 30, 2007. Waukesha County Department of Public Works has hired Hoffman Construction Company to do this work and R.A. Smith & Associates, Inc. (name changed to R.A. Smith National, effective March 17, 2008) to manage the project. The construction will include the removal of the existing road from a point west of C.T.H. "Y" to a point west of C.T.H. "V," the replacement with new asphaltic boulevard roadway with left turn lanes, concrete curb and gutter, and driveway approaches. The work also includes rubblizing the road from a point west of C.T.H. "V" to a point west of Colgate Road and overlaying the rubblized surface with 6.5" of asphalt.
C.T.H. "Q" is anticipated to be done in three stages. The first stage has two parts. In Stage 1A the north side of the road from C.T.H. "Y" to C.T.H. "V" will be constructed. Stage 1B includes the rubblized section from C.T.H. "V" to Colgate Road. The rubblized section will be done with that section of the road closed from April 30 through May 24. There will be a detour utilizing S.T.H. 175 north to S.T.H. 167, west to S.T.H. 164 and south to C.T.H. "Q."
Stage 2 will place traffic on the newly constructed roadway and construct the south half of the road from C.T.H. "Y" to C.T.H. "V."
Stage 3 will be constructing the cross over areas west of C.T.H. "V" and west of C.T.H. "Y." The contractor shall maintain access to all businesses at all times. Except for the detour, C.T.H. "Q" and all side roads will be open during construction at all times. Residential driveways may be closed periodically, but residents shall be given reasonable notice prior to limiting access.
All businesses on the project site are encouraged to inform their customers of the construction process.
If you have any existing drain or field tile, please contact me so that I can ensure these tiles are connected to the new storm sewer system.
I would like to take this opportunity to remind everyone of the safety hazards around a construction project. Driving at a reduced speed will make it safer for everyone concerned. The speed limit will be reduced to 25 MPH within the construction limits for the duration of the project. Also, a highway project makes a very dangerous but attractive playground for children. Please warn them of the dangers and please keep them clear of the construction area.
If you have any questions or requests, please contact Ted Kautzman; on site Project Engineer, for Waukesha County at 262-317-3387. My normal business hours are between 6:30 a.m. and 4:30 p.m.; however, I will be able to stay after hours if prior arrangements are made.
Contact Information:
Theodore D. Kautzman
Project Engineer,
R.A. Smith National
16745 W. Bluemound Road
Brookfield , WI 53005-5938
Phone: 262-317-3387
Pager: 262-451-0348
Edward Hinrichs
Project Manager,
Waukesha County Department of Public Works
Administration Center
1320 Pewaukee Road
Waukesha, WI 53188
Phone: 262-548-7740
|
UPDATES
Week of April 27, 2008
The contractor will be mobilizing on site to prepare to install a liner in the pond which is located a quarter mile west of Lannon Road on the south side of County Line Road.
This work will include installing erosion control, removing some fencing, and installing a tracking pad and by-pass pipes for the inflow into the pond.
Week of May 4, 2008
The contractor will be placing the liner in the pond and doing miscellaneous landscaping throughout the project. This work includes:
- Creating a work site in the fore bay of the pond
- Excavating, grading and installing the liner
- Restoring the landscaping of the pond area
- Restoring damaged topsoil and sod through the length of the project
- Installing flumes as needed
Weather permitting, all work is scheduled to be completed by May 16, 2008.
If you have any questions or requests, please contact Ted Kautzman; on site Project Engineer, for Waukesha County at 262-317-3387
Contact Information:
Theodore D. Kautzman
R.A. Smith National
16745 W. Bluemound Road
Brookfield, WI 53005-5938
Phone: 262-317-3387
Pager: 262-451-0348
Edward Hinrichs
Project Manager
Waukesha County Department of Public Works
Administration Center
1320 Pewaukee Road Waukesha, WI 53188
Phone: 262-548-7740
March 2008
In spring 2008 corrective work will be completed and a liner installed on the pond fore bay.
If you have any questions or requests, please contact Ted Kautzman; on site Project Engineer for Waukesha County at 262-317-3387. My normal business hours are between 6:30 a.m. and 4:30 p.m. The field office on Amy Belle Rd. has been removed.
Week of December 10, 2007
All substantial work has been completed and the roadway is open. There may be miscellaneous work to be completed by the contractor over the winter and into the spring of 2008. The mailboxes have been replaced.